DPWH probes Gandara Brigde collapse, targets April 2027 completion

DPWH Secretary Banoy Lopez inspected the Gandara II Parallel Bridge on November 20 following the collapse of two girders, as officials address safety concerns and project delays.

Jazmin Bonifacio 6 days ago
Posted on November 21, 2026 at 10:14 AM

Tacloban City — The collapse of two girders at the Gandara II Parallel Bridge has raised questions about construction safety and project supervision, even as the Department of Public Works and Highways (DPWH) works to repair the damage and keep the project on schedule.

DPWH Secretary Banoy Lopez visited the construction site on November 20 to inspect the damage following the collapse of the two girders during construction.

Lopez ordered the contractor to carry out immediate corrective measures and closely monitor the remaining work to prevent further problems and delays.

The DPWH said its technical assessment did not identify substandard materials as the cause of the collapse. It also reported that the bridge’s piers and abutments remained stable.

However, the department has yet to publicly explain in detail what caused the two girders to fall. Questions also remain about the construction procedures, site supervision, and safety checks conducted before the incident.

The names of the contractor and project engineer, as well as the findings on possible lapses in construction or supervision, have yet to be established in the information released by the department.

The technical assessment is also important in determining whether the collapse resulted from installation procedures, structural design, construction methods, or other factors. An independent engineering review could help verify the findings.

P92.6-MILLION PROJECT TARGETS APRIL 2027 COMPLETION

The incident also puts the project’s timeline under scrutiny, with the DPWH targeting April 2027 to finish the reconstruction and open the bridge to motorists.

The 70-meter Gandara II Parallel Bridge project has a budget of P92.616 million for Phase 1. Once completed, it is expected to improve traffic flow and provide safer passage for motorists and pedestrians.

During his November 20 visit, Lopez reminded the contractor to follow the project schedule and avoid further delays.

He also clarified that the Phase 1 project costs around P92 million, not P512 million, as claimed in information circulating publicly.

However, the DPWH has yet to disclose the project’s latest completion rate, how much of the budget has already been spent, and whether repairing the damaged girders will require additional funding.

These figures would help determine how much work remains and whether the contractor can meet the April 2027 deadline.

It also remains unclear who will shoulder the cost of replacing or repairing the damaged girders and whether the incident will affect the project’s approved budget.

QUESTIONS ON CONSTRUCTION SAFETY

While the DPWH reported that the bridge’s piers and abutments remained stable, the collapse of the two girders has raised concerns about how construction work was carried out and monitored.

The department needs to explain what caused the girders to fall and whether the contractor followed the approved construction plans and safety procedures.

The public also needs to know whether any lapses occurred, who was responsible for overseeing the work, and what steps will be taken to prevent a similar incident.

With P92.616 million allocated for Phase 1, residents and motorists have reason to expect a bridge built according to safety standards and completed within the promised schedule.

For now, the DPWH has set April 2027 as the target for completion. Whether it can meet that deadline, while addressing the damage and questions surrounding the collapse, remains to be seen.